Costa Mesa Sewer Rehabilitation Along the I-405

Home >> Construction >> Costa Mesa Sewer Rehabilitation Along the I-405

This project is continuing with sewer rehabilitation work. We appreciate your patience as this work is being done to enhance the aging infrastructure to extend the life of the regional sewer system another 25-30 years.

Upcoming Work

LOCATION: Various locations along 405 Freeway between Fairview Rd. and Bristol St.

2025.05 Upcoming CIPP Work for Along the 405 Project

What:  A bypass system consisting of above ground piping and bypass pumps will be installed to temporarily reroute sewer flows to allow for the rehabilitation to occur without interrupting sewer service to the community. Other work includes pipeline cleaning, pre-inspection, rehabilitation, post-inspection, and removal of the bypass system. 

When:  Starting May 27 – July 2025*

Hours:   Monday – Friday, 7 a.m. – 5 p.m.

Impacts:

  • Increased noise due to construction activity.
  • Temporary above-ground piping primarily along the flood control channel.
  • Generator noise from bypass pumps. The pumps are needed to push flows out of the sewer pipe and into the above ground piping. Noise barrier will enclose the bypass pump area to reduce the transmission of noise.

Additional Information:  The actual rehabilitation work will be done in several segments. Each segment requires continuous uninterrupted work hours and may extend outside normal working hours, including night work. More detail and information will be provided when those dates are scheduled.


LOCATION: Pacific Arts Plaza on Park Center Drive

2025.05 Park Center Drive Civil Improvements

What:  Manhole access improvements. This will include modifying the gate and driveway entrance location to an existing manhole. 

When: Starting June 2 and lasting approximately 2 weeks*

Hours: Monday – Friday, 7 a.m. – 5 p.m.

Impacts:  No full road closures are to be expected. The impacts are anticipated to be minimal outside the work area other than increased noise and activity due to the construction.

*All dates and times are subject to change due to operational factors or inclement weather.


Work is also occurring at the OC San Main Street Pump Station in the City of Irvine and Airway Avenue and Airport Loop Drive in the City of Costa Mesa. See ocsan.gov/airwayairport for more information.

Project Description

This project will rehabiliate approximately 4 miles of the regional sewer pipeline that runs along the I-405 freeway in the City of Costa Mesa. Project elements include the rehabilitation of gravity sewer pipelines, manhole structure rehabilitation, and manhole access improvements. The project also includes the rehabilitation of sewer pipelines that cross under the I-405 freeway. 

Project Map

Stay In The Know

Community Liaison:
(714) 378-2965

Email:
constructionhotline@ocsan.gov

Sign up for text alerts:
click here

Related Construction

Site Location

Construction Schedule

Summer 2024 - early 2026*

Construction Budget

$43.4 million